PERT Chart Closer Look
For each task in a PERT chart, specify the task name, which is the name of the work package, by default.
Task Name
CRM System Integration
Duration
ID
001 48 days
End Date
Start Date Dec 16, 2016 Feb 02, 2017
Responsible Person
Peter
• An ID that uniquely identifies the task.
• The planned start and finish date of the task. Note that a task can only be start if the depending task is completed. In other words the
start date of a task must be greater than the finish date of all the depending tasks.
• The duration, which is the number of days between start and end date. And, The person who are responsible for this task.